Unplanned

Notification of Unplanned Unavailability

Please be advised that the flow to the National Grid from Bacton/SEAL/St. Fergus has been reduced for an unplanned outage:

Event ID  Message Type Facility  Time published  Time of event  Expected End Actual End Volume impact mcm/day 
20190204SL New Bacton Shell 15:30
04/02/2019
15:00
04/02/2019
Unknown 5.43
20190204SL  Final Bacton Shell 20:05
04/02/2019
15:00
04/02/2019
N/A 19:30 Production restarted offshore
20190209SF New St Fergus 23:44
09/02/2019
23:00
09/02/2019
Unknown 9.40
20190209SF Final St Fergus 23:15
10/02/2019
23:00
09/02/2019
N/A 21:50
10/02/2019
11.0
20190607SF New St Fergus 11:30
07/06/2019
09:30 (GMT)
07/06/2019
Unknown 8.0 Mm3/d
20190607SF Final St Fergus 05.30 
08/06/2019
09:30 (GMT) 07/06/2019 Unknown 05:00 (GMT)
08/06/2019
 
St Fergus capacity restored
20190814SF New St. Fergus 17:00
14/08/2019
06:00
20/08/2019
Unknown Unknown (to be evaluated in the coming days)
20190814SF Revision 1 St. Fergus 08.55
17/08/2019
06:00
18/08/2019
Unknown

18 & 19/08/2019 – 5Mm3/d
From 20/08/2019 Onwards – 12Mm3/d

20190814SF Revision 2 St Fergus 17:00
18/08/2019

06:00
18/08/2019

Unknown 19/08/19 – 2.5Mm3/d
20/08/2019 – 10Mm3/d
21/08/19 Onwards – 12-14Mm3/d
20190814SF Revision 3 St Fergus ASAP 06:00
18/08/2019
Early December
2019
19/08/19 – 2.5Mm3/d
20/08/2019 – 10Mm3/d
21/08/19 Onwards – 12-14Mm3/d
02/09/19 Onwards – 06-10Mm3/d
20190902BN New Bacton Shell 18.00
02/09/2019
14:28
02/09/2019
Unknown 7.2 mcm/day Operational Issues & Planned Maintenance
20190902BN FINAL Bacton Shell 18.45
02/09/2019
14:28
02/09/2019
Unknown 18:09 Operational Issues Resolved

The information given is in good faith to the best of our knowledge at the time of posting, but no warranty is given as to its accuracy or completeness.

Planned

Notification of Planned Unavailability

Please be advised that the flow to the National Grid from Bacton/SEAL/St. Fergus will be reduced for the following unplanned outage:

Event ID Message Type Facility Time Published Time of Event Expected End Actual End Volume impact mcm/day
20190219SF New St Fergus 17:20
06/27/2018
06:00
19/02/2019
06:00
20/02/2019
16 mcm/day (6-12hr plant outage for ESD testing)
20190801SL New SEAL 11:30
31/12/2018
06:00
01/08/2019
06:00
05/08/2019
NA 14 mcm/day – planned maintenance at Bacton terminal.
20190801SL Final SEAL 12:40
03/08/2019
12:30
03/08/2019
06:00
05/08/2019
12:30
03/08/2019
Terminal maint completed
20190309BN New Bacton 13:30
08/01/2019
06:00
09/03/2019
06:00
10/03/2019
NA 11.5 mcm/day – planned maintenance at Bacton terminal.
20190908BN New Bacton 13:30
08/01/2019
06:00
08/09/2019
06:00
11/09/2019
NA 10.0 mcm/day – planned maintenance at Bacton terminal.
20190908BN Final Bacton 13:10
09/12/2019
06:00
08/09/2019
06:00
12/09/2019
11:30
12/09/2019
Terminal maint completed
20190309BN FINAL Bacton 11:00
12/04/2019
06:00
09/03/2019
06:00
10/03/2019
10:00
10/03/2019
Bacton available to receive gas deliveries.
20190203SF New St Fergus 17:15
10/01/2019
06:00
03/02/2019
06:00
08/02/2019
15 mcm/d
20190203SF Revision St Fergus 15:45
17/01/2019
06:00 03/02/2019 06:00 08/02/2019 17.5 mcm/d
20190203SF Revision St Fergus 18:00
05/02/2019
 06:00
03/02/2019
06:00 
11/02/2019
15 mcm/d
20190203SF Revision St Fergus 16:00
07/02/2019
06:00 03/02/2019 18:00 08/02/2019 17.5 mcm/d
Approximate 1-2 day ramp up expected.
20190203SF Revision St Fergus 02:50
09/02/2019
06:00 03/02/2019 12:00
09/02/2019
15 mcm/d
20190203SF FINAL St Fergus 13:35
09/02/2019
06:00 03/02/2019 12:00 09/02/2019 13:00 09/02/2019 Downstream capacity restored
20190219SF Revision St Fergus 14:30
15/02/2019
06:00 12/03/2019 06:00 13/03/2019 16 mcm/day (6-12hr plant outage for ESD testing)
20190219SF Revision 2 St Fergus 12:00
06/03/2019
POSTPONED – Revised date TBC. POSTPONED – Revised date TBC. POSTPONED – Revised date TBC.

ESD Test planned for 12th March 2019 is postponed.

New date to be issued shortly.

20190325SF New St Fergus 14:15
08/03/2019
06:00 25/03/2019 06:00 30/03/2019

First day impact during ESD test - 16 mcm/day (6-12hr plant outage for ESD testing).

Following days partial impact of 5 mcm/day.

20190325SF Revision 1 St Fergus 01:25
22/03/2019
06:00 25/03/2019 06:00 29/03/2019

Partial Impact on gas day 25th – 27th of 5mcm/day.

Full impact on gas day 28th March - 16 mcm/day (12hr plant outage for ESD testing).

20200220SF New St Fergus 13:45
29/03/2019
06:00 20/02/2020 06:00 21/02/2020 16 mcm/day (12hr plant outage for ESD testing).
20200721SF New St Fergus 13:45
29/03/2019
06:00 21/07/2020 06:00 11/08/2020 Total Plant Shutdown – zero flow capacity.
20190325SF Final St Fergus 07:45
30/03/2019
06:00 25/03/2019 06:00 29/03/2019  06:00 29/03/2019 Downstream capacity restored
20190601SL New SEAL 10:00
12/04/2019
06:00
01/06/2019
06:00
06/06/2019
NA 14 mcm/day – liquid export route unavailable.
20190601SL Final SEAL 10:20 04/06/2019 06:00
01/06/2019
06:00
06/06/2019
14:30
02/06/2019

Liquid Export Route available

20190829SL New SEAL 18:00
27/08/2019
08:00
29/08/2019
18:00
29/08/2019
NA 14 mcm/day – SEAL Bacton Plant Unavailability
20190829SL Final SEAL 18:45
29/08/2019
08:00
29/08/2019
18:00
29/08/2019
18:00
29/08/2019
SEAL Bacton Plant available

The information given is in good faith to the best of our knowledge at the time of posting, but no warranty is given as to its accuracy or completeness.

More in Upstream oil and gas

North Sea operated assets

Discover more about Shell’s oil and gas operated assets in the North Sea including capacity and facilities information.

SEGAL system

The SEGAL system is made up of two wet gas transportation pipelines, the St. Fergus gas terminal, Fife NGL terminal and Braefoot Baytanker loading facility.

Published key terms

Data published in accordance with the Code of Practice on Access to Upstream Oil and Gas Infrastructure on the UK Continental Shelf (ICOP) and the Gas Act (1995).

Contracting and procurement

Documents provided by the Contracting and Procurement Management group for information and guidance on how to do business with us.