Notification of Planned Unavailability

Please be advised that the flow to National Grid from Shell Bacton will be reduced for planned maintenance:

Date of outage Relevant ASEP Loss of Volume (mcm/d) Duration of outage
13/09/14 Bacton 18 2 days

Please be advised that the flow to National Grid from Shell St Fergus will be reduced for planned maintenance:

Date of outage Relevant ASEP Loss of Volume (mcm/d) Duration of outage
07/04/2014 St Fergus 25 6-12 hours
15/08/2014 St Fergus 12 (capacity reduction)

Module now expected to be fully available from Monday 20th October 2014.

 

The information given is in good faith to the best of our knowledge at the time of posting, but no warranty is given as to its accuracy or completeness.

Unplanned Unavailability

Please be advised that the flow to National Grid from Shell St Fergus has been reduced for an unplanned outage:

Time of outage Relevant ASEP Loss of Volume (mcm/d) Anticipated duration
13:25 21/02/2014 St Fergus 11.1 0.5 hrs
06:00 16/09/2014 St Fergus 10.41 10 hrs

The information given is in good faith to the best of our knowledge at the time of posting, but no warranty is given as to its accuracy or completeness.

Latest and historic information

2015 Upstream operational information

2013 Upstream operational information

More in this section

North Sea operated assets

Discover more about Shell’s oil and gas operated assets in the North Sea including capacity and facilities information.

SEGAL system

The SEGAL system is made up of two wet gas transportation pipelines, the St. Fergus gas terminal, Fife NGL terminal and Braefoot Baytanker loading facility.

Published key terms

Data published in accordance with the Code of Practice on Access to Upstream Oil and Gas Infrastructure on the UK Continental Shelf (ICOP) and the Gas Act (1995).

Contracting and procurement

Documents provided by the Contracting and Procurement Management group for information and guidance on how to do business with us.